06 · LEAD TIMES

Plan it from PO to arrival port

Lead times only mean something when you know when the clock starts. Pick a product, a quantity and a destination, and the planner lays out every milestone of a real T&A calendar.

Knit bulk
45–60 days
Denim bulk
60–75 days
To Hamburg
30–36 days

T&A PLANNER

Your time-and-action calendar

Typical durations from our last 200 orders. Your merchandiser confirms the dates against live capacity.

Sampling

EX-FACTORY

—

ARRIVAL (ETA)

—

PO TO ARRIVAL

—

    OPEN CAPACITY

    What's still bookable

    A slot is confirmed when the PP sample is approved and the LC or advance is received.

    Production capacity booked, by ex-factory month (updated 4 November 2026)
    Ex-factoryKnitDenim
    Dec 2026
    Full
    Full
    Jan 2027
    4% open
    8% open
    Feb 2027
    16% open
    21% open
    Mar 2027
    32% open
    39% open
    Apr 2027
    51% open
    56% open
    May 2027
    69% open
    72% open

    SEA FREIGHT

    Transit from Chattogram

    Typical port-to-port days, including transhipment in Colombo or Singapore. Air freight from Dhaka takes 4–7 days, door to door.

    DestinationTypical transitSailings
    Hamburg30–36 daysWeekly
    Rotterdam29–35 daysWeekly
    Antwerp30–36 daysWeekly
    Felixstowe31–38 daysWeekly
    New York / New Jersey38–45 daysTwice weekly
    Los Angeles / Long Beach30–36 daysTwice weekly
    Montreal40–48 daysWeekly

    NEXT STEP

    Send a tech pack. Get a costed reply within 48 hours.

    A merchandiser reviews every request, checks it against our open capacity and replies with an indicative FOB, MOQ and timeline. NDA on request, before you share a single sketch.